Which estimating method is typically prepared after the preliminary design is completed?

Prepare for the ARE 5.0 Programming and Analysis (PA) Exam with comprehensive flashcards and multiple-choice questions. Each question offers detailed explanations and hints to enhance your understanding. Gear up for success!

The area method is typically prepared after the preliminary design is completed because it provides a way to estimate construction costs based on the square footage of the building types being proposed. Once a preliminary design is developed, including the layout and the general dimensions of the project, architects and estimators can use the area method to calculate expected costs by applying square footage rates, which can be derived from historical data or market surveys.

This approach enables a relatively quick estimation process based on the overall size of the project, making it suitable during the design development phase when more specific cost details may not yet be available but an understanding of the project scale is clearer. As such, it aligns well with the timing after preliminary design completion when decisions about space and form have been substantially made.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy